Refurbishment of "Alter Kaiser-Wilhelm-Tunnel" (AKWT) VP08
Construction of the "Rheda 2000" slab track system
Client
DB Netz AG
Project volume
EUR 7.46 million
Construction time
09/2016-05/2017
Services
Construction of slab track system "Rheda 2000" and walkways in the 4,205 m long single tracked AKWT tunnel, construction of transition sections and auxiliary works.
Construction work carried out:
- Construction of 4,273 m of the "Rheda 2000" slab track system in a single-track tunnel including transition areas
- Ballasted tracks in precuts (incl. 3 turnouts)
- Construction of walkways
- maintenance of railway bridge, bridge road and brickwork rehabilitation
- Gap closing of turnouts