Hockeroda–Probstzella track renewal
12,701 m of track renewal with ballast cleaning using assembly line techniques
Client
DB Netz AG Leipzig
Project volume
EUR 3,500,000
Construction time
14.07.2016 - 03.09.2016
Track / underground construction:
- 12,701 m of track renewal using assembly line techniques with ballast cleaning/preparation
- Renewal of three culverts and two double-track level crossings
Associated services:
- 8,400 m of deep drainage cleaning and flushing;
- Construction of 12,700 m of side paths;
- Construction of 165 m of side path shoring